Tab 1

  • FS: SC AVENSA CONSULTING SRL - leader &TRN INGENIRIA Y PLANIFICACION DE INFRAESTRUCTURAS SA - partner TP: SC AVENSA CONSULTING SRL - general contractor & SC BODO INVEST SRL - subcontractor

  • Romania

  • Vaslui Municipality

  • Structural Funds POR 2007 - 2013

  • FS: 10.12.2008 - 28.03.2009; TP: 12.10.2009-12.11.2009

Tab 2

Rehabilitation, modernization and extension of public transport infrastructure, creating an intermodal terminal, rehabilitation, extension of public lighting in Vaslui Municipality

 

General objective: Rehabilitation of the  urban infrastructure of the city Vaslui by implementing environmentally friendly mobility solutions at the level of public road transport in the urban action area until 2015, thereby improving the healthy life conditions at the level of the urban action area, thus enhancing the attractiveness of the North-East region, the quality of life and the creation of new jobs.

Specific objective: implementation of ecological mobility solutions in pleasant and safe conditions by developing environmentally friendly public transportation by rehabilitating and expanding the trolley line, and by rehabilitation and extension of the public lighting system aimed at energy efficiency in the urban action zones and through implementation of intermodal solutions for efficient public transport system in Vaslui city, during the 21 months through:

  • Rehabilitation of 9.550 m trolley line and extension of the trolley line with 4,000 m:
    • Rehabilitation of the trolley line on Decebal Street, Stefan cel Mare Street, Republicii Street;
    • Extension of the trolley line: Stefan cel Mare Street and National Highway
    • Rehabilitation of 11,031 m of public lighting line and public lighting extension with 4130 meters:
    • Rehabilitation of public street lighting on Decebal Street, Stefan cel Mare Street, Republicii Street.
    • Extension of the trolley line: Stefan cel Mare Street and National Highway
  • Creating an intermodal terminal on an area of 19,505 sqm on Decebal Street, with the following characteristics: Ac body C1 (Main building intermodal terminal function) = 845.36 sqm; Ad body C1 = 1072, 12 sqm; Ac = Ad body C2 (secondary building functioning as lockers for staff) = 110.40 sqm; Ac = Ad Washing plant = 160, 0 sqm.

 

Tab 3

The main activities of project provided:
Ensuring consultancy services, economical and technical, for the funding documentation corresponding to the individual project for accessing the Regional Operational Programme - Axis 1

Drafting the economic and technical documentation (technical project, including certified checks on specialties, specifications, construction details, approvals, DTAC);
Performing investment studies: topographical survey, geotechnical survey, technical expertise, energy audit;
Ensuring technical support during the performance of work until the final acceptance report.